Configure a Bin Chain in ROS
To manually configure Bin Chaining:
-
Open a job that is desired to use bin chains. Do not start the job.
-
In the Tank Assignment section, select the Bin Chain icon. The Bin Chain Management prompt will display.
Note: If the Bin Chain icon is green, ROS has automatically chained the products with the same Product Mix name. If the icon is gray, there are no chained products or a manual chain may be configured.
-
Select the Manual Group box.
-
Select and hold the Add Bin Chains icon to add nodes. The primary product window will open.
-
Configure the Primary Product, Bin Chain Name, and Rate Information.
-
Select the Add Node icon in the selected chain field to add other bins to the product.
-
Select the advanced method for bin switching. This can either be done when the Bin Level sensor alarm is triggered, when there is an empty tank, or a low tank alarm is triggered.
-
Repeat the process for each empty chain. A minimum of four products/nodes are required to have multiple chains.
-
After completing a bin chain, it is possible to reverse the bin chain order by pressing Reverse. This changes the order of the links (instead of 1 - 3 the order would become 3 -1).
Note: After a bin chain has been configured, the user can create and select chain profiles. See Configure Chain Profiles for more information on chain profiles.